SITE PROGRESS UPDATE JULY 2023

The Stadium continues to see significant progress with the finalisation of cladding works in brand-new Town Square’s atrium and roof areas. Internal fit-outs to Town Square Level 1 and 2 have also progressed along with the energisation of the area. On the eastern side of the Stadium, City Edge is expected to see major developments with internal fit-out works, installation of external cladding and energisation scheduled to progress throughout July and August. In other works, removal of the Temporary Ramp from Wurundjeri Way to City Edge Concourse will be carried out during mid-July (works will be carried out as night works and will involve closure of remaining lane on Wurundjeri Way). A letter drop to neighbouring properties will be conducted one week prior to works commencing.

 

Thank you for your patience while construction is underway. The team is doing everything possible to ensure disruption is minimised.

Table of Upcoming Works:

 

Naming Partner

Stadium Partners

Home Teams